“But you weren’t going to perform anyway!”: A new hurdle when invoking Force Majeure

Classic Maritime Inc v Limbungan Makmur SDN BHD [2019] EWCA Civ 1102

Simon Rainey QC and Andrew Leung

Is it necessary when a party seeks to rely on a force majeure or exceptions clause to show that it would have performed “but for” the force majeure or excepted event? And if the party is liable for failing to perform, but performance would have been impossible in any event, is the innocent party entitled to damages?

These important questions were considered by the Court of Appeal in Classic Maritime Inc v Limbungan Makmur SDN BHD [2019] EWCA Civ 1102. The judgment, which is the sequel to the first instance decision discussed here, clarifies that:

  1. Contrary to what textbooks such as Chitty and Treitel on Frustration and Force Majeure suggest, there is no general principle that it is not necessary to show “but for” causation in order to invoke a force majeure or exceptions clause.
  • The innocent party is entitled to substantial damages even if it would never have received performance in any event.

The dam burst and the COA

The litigation was fuelled by the Samarco dam burst on 5 November 2015. The charterer under a COA, Limbungan, claimed it was prevented from supplying cargoes for shipment as a result and was excused from having to perform under Clause 32 of the COA, which provided in material part:

“Neither the Vessel, her Master or Owners, nor the Charterers, Shippers or Receivers shall be responsible for…failure to supply, load…cargo resulting from: Act of God…floods…landslips…accidents at mine or production facility…or any other causes beyond the Owners’, Charterers’, Shippers’ or Receivers’ control; always provided that such events directly affect the performance of either party under this Charter Party.”

The first instance decision

At first instance, Teare J held that though the dam burst had rendered performance impossible, Limbungan could not rely on Clause 32 as it required the charterer to prove that it would have performed but for the collapse of the dam, and Limbungan would have defaulted anyway. However, the owner, Classic, was only entitled to nominal damages. Even if Limbungan had been able and willing to perform, the dam burst would inevitably have prevented performance. The compensatory principle would be breached if Classic was awarded substantial damages when it would never have received freight in any event.

The Court of Appeal’s decision

The Court of Appeal upheld Teare J’s decision that Clause 32 required Limbungan to prove but for causation and reversed his decision in relation to damages.

Limbungan had submitted that the House of Lords decision in Bremer Handelgesellschaft v Vanden Avenne-Izegem PVBA [1978] 2 Lloyd’s Rep 109 laid down the general principle that a party relying on force majeure need not show it would have performed but for the force majeure event.

However, the Court of Appeal, like Teare J, treated Bremer v Vanden as a case concerning a “contractual frustration” clause (Clause 21 of the GAFTA 100 form), i.e. a clause which automatically discharged the parties from an obligation to perform in the future, much like the common law doctrine of frustration. The automatic cancellation effected by Clause 21 meant it was not necessary to meet the test of but for causation.

Starting from first principles, it was open to the parties to agree a clause which only excused non-performance if that test was met. The Court of Appeal considered that Clause 32 was just such a clause. Unlike the “contractual frustration” clause in Bremer v Vanden, it was an exemption clause which relieved a party of liability for a past breach. It was hard to see why the dam burst should make any difference to Limbungan’s liability when it was never going to perform anyway.

On the issue of damages, what Teare J thought was an orthodox application of the compensatory principle the Court of Appeal viewed as a “sleight of hand”. When assessing Classic’s loss, the Judge should have compared the freights Classic would have earned with the actual position it was in due to Limbungan’s breach. Teare J had instead drawn a comparison between Classic’s actual position and its position if Limbungan had been ready and willing to perform.

The Court of Appeal distinguished the present case from two cases in which events occurring after a breach of contract were taken into account:

  1. In The Golden Victory [2007] 2 A.C. 353, the House of Lords held that the owners could not recover hire for the full-term of a charterparty prematurely cancelled by the charterers. The charterparty would not have run its full course anyway as the charterers would have lawfully cancelled due to the Second Gulf War.
  • In Bunge v Nidera [2015] 3 All E.R. 1082, the Supreme Court held that a buyer had suffered no loss despite the repudiation of a sale contract by the seller. A subsequent embargo would however have prevented the sale from taking place in any event.

Both cases were however concerned with assessing damages for an anticipatory breach. Contrastingly, the present case was concerned with an actual breach. Since Clause 32 gave Limbungan no defence to liability, Limbungan had to pay damages for failing to perform.

Comment

The Court of Appeal has underlined the fact that, whatever the current understanding of Bremer v Vanden in the textbooks,there is no default position whereby it is unnecessary to prove but for causation in order to rely on a force majeure or exceptions clause. The specific Force Majeure remedy afforded by Clause 21 of GAFTA 100 was held to be the reason that clause did not import a requirement of but for causation. Why this remedy should determine the test for causation is not entirely clear, when the effect of contractual cancellation and an exemption from liability is for practical purposes the same: the non-performing party cannot be successfully sued.

In other respects, this case presents a number of novelties:

  1. The Court of Appeal held that Clause 32 was not even a force majeure clause, but an exemption clause. It was not previously clear that these categories were mutually exclusive (see e.g. Lewison, Interpretation of Contracts, 13.02).
  • Both Treitel and Lewison suggest in the light of the authorities that a clause which makes provision for the consequences of supervening events which occur without the fault of either party and are beyond their control (i.e. Clause 32) defines the parties’ obligations rather than operating as an exemption clause. This now needs to be reconsidered.
  • The Court of Appeal’s take on The Golden Victory and Bunge v Nidera is that subsequent events and their potential effect on the parties’ rights and obligations are only relevant when assessing damages caused by an anticipatory breach accepted as terminating the contract. They are not relevant in the case of an actual breach. This is arguably a new development and suggests there is not one compensatory principle, but two.

Permission to appeal was refused by the Court of Appeal but an application for permission to appeal is being made to the Supreme Court. The authors are Counsel for Limbungan and appeared below and in the Court of Appeal.

Published by

Simon Rainey KC

Simon Rainey KC is one of the best-known and most highly regarded practitioners at the Commercial Bar with a high reputation for his intellect, advocacy skills, commercial pragmatism and commitment to client care. He has established a broad commercial advisory and advocacy practice spanning substantial commercial contractual disputes, international trade and commodities, energy and natural resources, insurance and reinsurance shipping and maritime law in all its aspects,. He appears in the Commercial Court and Court of Appeal and also the Supreme Court (with two recent landmark victories in NYK v Cargill [2016] UKSC 20 and Bunge SA v Nidera SA [2015] UKSC 43.) He regularly handles Arbitration Act 1996 challenges. He has extensive experience of international arbitration, regularly appearing as advocate under all of the main international arbitral rules (LCIA; SIAC, UNCITRAL; ICC, Swiss Rules etc) and also sitting as arbitrator. Current examples of his work as counsel are in arbitration before the Permanent Court of Arbitration in a US 13billion gas supply dispute; under Nigerian Law and seat in relation to an offshore oilfield redetermination dispute between oil majors, under UNCITRAL Rules in a mining supply take or pay dispute involving one of the world’s leading mine conglomerates; an ICC arbitration concerning a new mine development in Russia and an ICC Dubai seat arbitration involving specialist offshore vessels and in associated s67 and s68 LCIA challenges in the A v B [2017] EWHC 3417 (Comm) litigation in the4 Commercial Court. Recent arbitral appointments include an ICC Paris seat arbitration concerning a power station failure, a French law and seat arbitration relating to an oil rig drilling contract, an offshore construction contract claim under SIAC Rules and a long-term ore supply contract claim under Swiss Rules. He is highly ranked by Chambers and Partners and Legal 500 as a first division international arbitration specialist (“Highly regarded for his expertise in handling high-profile international arbitrations in connection with complex oil and gas, banking and finance and trade issues. He is well known for his prowess in advising and representing clients in disputes in countries as far flung as Turkey, Russia, the USA, China and India” 2018; “Incredibly good, with a particular skill in reducing the complicated to the elegantly simple, which when you're trying to present a case to a tribunal or court is one of the more valuable things you need to have” 2018; “Clearly now one of the top commercial silks and a delight to work with.” 2018; “A mixture of brilliance and brevity, his written submissions are like poetry” 2018), He was nominated for “International Arbitration Silk of the Year 2017” by Legal 500 and has also been awarded “Shipping & Commodities Silk of the Year” 2017 by both Chambers & Partners and Legal 500. He sits as a deputy High Court Judge in the Commercial Court and is Honorary Professor of Law, Business and Economics, Swansea University.

One thought on ““But you weren’t going to perform anyway!”: A new hurdle when invoking Force Majeure”

  1. Commenting solely on the point of recoverability of substantive damages, I do not think the Court of Appeal’s decision alters the compensatory principle of placing the innocent party in the same financial position as if the contract had been performed. The question is – was there an obligation to perform? The answer is Yes, because the Charterer had two modes of performance. Performance by one mode became impossible (due to the dam burst). Although performance by the other mode also became impossible (because the Charterer’s supplier refused to supply), as a matter of law, it did not amount to a frustrating event ([2018] EWHC 2389 (Comm), Para 64 – reference to The Mary Nour which held that the seller could not rely on his supplier’s refusal to supply goods as a frustrating event). Absent a finding of frustration, the Charterer was still under an obligation to perform and a failure of which would entitle the Shipowner to substantive damages.

Leave a Reply